Q. The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is

  • (A) 19
  • (B) 14
  • (C) 24
  • (D) None of these

A

Admin • 802.91K Points
Coach

Q. Consider the following activities in a building construction: 1. Concreting of roofslabs 2. Brick-jelly lime concrete terracing 3. Erection of form work forslab 4. Construction of parapet wall in terrace

  • (A) 1, 3, 2, 4
  • (B) 3, 1, 4, 2
  • (C) 3, 1, 2, 4
  • (D) 1, 3, 4, 2

A

Admin • 802.91K Points
Coach

Q. Military organisation is known as

  • (A) Line organisation
  • (B) Line and staff organisation
  • (C) Functional organisation
  • (D) None of these

A

Admin • 802.91K Points
Coach

Q. Mobilization advance up to 10% of the cost of work is given to a contractor

  • (A) On commencement of work at site for payment of loan taken by him
  • (B) For the purchase of construction materials
  • (C) For the payment of advances to labour and otherstaff
  • (D) For all activities required to start the work at site on finalization of the contract document

A

Admin • 802.91K Points
Coach

Q. Pick up the PERT event from the following:

  • (A) Digging of foundation started
  • (B) Digging of foundation completed
  • (C) Laying of concrete started
  • (D) All the above

A

Admin • 802.91K Points
Coach

Q. A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is

  • (A) Rs. 4,75,000
  • (B) Rs. 5,75,000
  • (C) Rs. 6,50,000
  • (D) Rs. 8,50,000

A

Admin • 802.91K Points
Coach

Q. The process of incorporating changes and rescheduling or replanning is called

  • (A) Resource levelling
  • (B) Resource smoothening
  • (C) Updating
  • (D) Critical path scheduling

A

Admin • 802.91K Points
Coach

Q. Completion of an activity on CPM network diagram, is generally known

  • (A) Event
  • (B) Node
  • (C) Connector
  • (D) All the above

A

Admin • 802.91K Points
Coach

Q. Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing. Reason R: If the angle of swing is decreased, the cycle time will be decreased. Select the correct answer.

  • (A) Both A and R is true and R is the correct explanation of A
  • (B) Both A and R is true but R is not the correct explanation ofA
  • (C) A is true but R is false
  • (D) A is false but R is true

A

Admin • 802.91K Points
Coach

Q. The salient feature of functional organisation is

  • (A) Strict adherence to specifications
  • (B) Separation of planning and design part
  • (C) Each individual maintains functional efficiency
  • (D) All the above