Q. In the critical path of construction planning, free float can be ?

  • (A) greater than total float
  • (B) equal to total float
  • (C) greater than independent float
  • (D) less than independent float

A

Admin • 802.91K Points
Coach

Q. When float or slack of an activity is positive ?

  • (A) it represents a situation where extra resources are available and the completion of project is not delayed
  • (B) it represents that a programme falls behind schedule and additional resources are required to complete the project in time
  • (C) the activity is critical and any delay in its performance will delay the completion of whole project
  • (D) any one of the above

A

Admin • 802.91K Points
Coach

Q. The time in which an activity will take to complete in case of difficulty, is called ?

  • (A) optimistic time
  • (B) most likely time
  • (C) pessimistic time
  • (D) none of these

A

Admin • 802.91K Points
Coach

Q. PERT analysis is based ?

  • (A) optimistic time
  • (B) pessimistic time
  • (C) most likely time
  • (D) all of these