Q. The early finish time of an activity is the ............ of early start time and duration of activity ?

  • (A) sum
  • (B) difference
  • (C) product
  • (D) ratio

A

Admin • 802.91K Points
Coach

Q. Which of the following are the guidelines for the construction of a network diagram ?

  • (A) Each activity is represented by one and only arrow in the network
  • (B) Dangling must be avoided in a network diagram
  • (C) Dummy activity consumes no time or resource
  • (D) all of the above

A

Admin • 802.91K Points
Coach

Q. The start or completion of task is called ?

  • (A) an event
  • (B) an activity
  • (C) a duration
  • (D) any one of these

A

Admin • 802.91K Points
Coach

Q. The total activity slack is equal to ?

  • (A) Late start time - Early start time
  • (B) Late finish time – Early finish time
  • (C) Latest allowable event occurrence time - Early finish time
  • (D) all of the above

A

Admin • 802.91K Points
Coach

Q. A dummy activity in a net work ?

  • (A) is represented by a dotted line
  • (B) is an artificial activity
  • (C) does not consume time or resources
  • (D) all of these

A

Admin • 802.91K Points
Coach

Q. The chart which gives an estimate about the amount of materials handling between various work stations stations is known as ?

  • (A) flow chart
  • (B) time chart
  • (C) travel chart
  • (D) operation chart

A

Admin • 802.91K Points
Coach

Q. The occurrence of the completion of an activity, is called its ?

  • (A) head event
  • (B) tail event
  • (C) dual role event
  • (D) none of these

A

Admin • 802.91K Points
Coach

Q. CPM is ?

  • (A) activity oriented
  • (B) event oriented
  • (C) time oriented
  • (D) resource oriented

A

Admin • 802.91K Points
Coach

Q. The optimistic time represents ?

  • (A) shortest possible time in which an activity can be completed if everything goes exceptionally well
  • (B) time in which the activity is normally expected to complete under normal contingencis
  • (C) time in which an activity will take to complete in case of difficulty
  • (D) none of the above

A

Admin • 802.91K Points
Coach

Q. The difference between the total float and free float is called ?

  • (A) duration
  • (B) interfering float
  • (C) critical activity
  • (D) none of these