Q. The most suitable type of equipment for compaction of cohesive soils is

  • (A) Smooth-wheeled rollers
  • (B) Vibratory rollers
  • (C) Sheep foot rollers
  • (D) Tampers

A

Admin • 802.91K Points
Coach

Q. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

  • (A) Started 5 days later
  • (B) Completed 5 dayslater
  • (C) Performed at slower rate in 15days
  • (D) All the above

A

Admin • 802.91K Points
Coach

Q. Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements

  • (A) Only (i) is correct
  • (B) (i) and (ii) are correct
  • (C) (i) and (iii) are correct
  • (D) (ii) and (iii) are correct

A

Admin • 802.91K Points
Coach

Q. A Milestone chart

  • (A) Shows the interdependencies of variousjobs
  • (B) Depicts the delay of jobs, if any
  • (C) Points outgoing ahead of schedule of jobs, if any
  • (D) None of these

A

Admin • 802.91K Points
Coach

Q. Earliest finish of an activity is always

  • (A) Greater than earliest event time of the following node
  • (B) Less than earliest event time of the following node
  • (C) Less than or equal to earliest event time of the following node
  • (D) Greater than or equal to earliest event time of the following node

A

Admin • 802.91K Points
Coach

Q. Critical path lies along the activities having total float

  • (A) Positive
  • (B) Negative
  • (C) Zero
  • (D) Same

A

Admin • 802.91K Points
Coach

Q. If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be

  • (A) 50 %
  • (B) Less than 50 %
  • (C) More than 50 %
  • (D) 100 %

A

Admin • 802.91K Points
Coach

Q. The critical activity has

  • (A) Maximum float
  • (B) Minimum float
  • (C) Zero float
  • (D) None of these

A

Admin • 802.91K Points
Coach

Q. For excavating utility trenches with precise control of depth, the excavation equipment used is

  • (A) Hoe
  • (B) Shovel
  • (C) Dragline
  • (D) None of the above

A

Admin • 802.91K Points
Coach

Q. PERT analysis is based on

  • (A) Optimistic time
  • (B) Pessimistic time
  • (C) Most likely time
  • (D) All the above