Q. The most popular type of organisation used for Civil Engineering Constructions, is

  • (A) Line organisation
  • (B) Line and staff organisation
  • (C) Functional organisation
  • (D) Effective organisation

A

Admin • 802.91K Points
Coach

Q. The probability of completion of any activity within its expected time is

  • (A) 50 %
  • (B) 84.1 %
  • (C) 99.9 %
  • (D) 100 %

A

Admin • 802.91K Points
Coach

Q. The performance of a specific task in CPM, is known

  • (A) Dummy
  • (B) Event
  • (C) Activity
  • (D) Contract

A

Admin • 802.91K Points
Coach

Q. Pre-tender stage requires

  • (A) Acquisition of land
  • (B) Selection of site
  • (C) Fmalisation of alignment of work
  • (D) All the above

A

Admin • 802.91K Points
Coach

Q. An event is indicated on the network by a number enclosed in

  • (A) A circle
  • (B) A square
  • (C) A triangle
  • (D) All the above

A

Admin • 802.91K Points
Coach

Q. If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is

  • (A) (t1 - t2) - t
  • (B) t - (t1 - t2)
  • (C) (t1 + t2) - t
  • (D) t + (t1 - t2)

A

Admin • 802.91K Points
Coach

Q. Free float for any activity is defined as the difference between

  • (A) Its earliest finish time and earliest start time for its successor activity
  • (B) Its latest start time and earliest start time
  • (C) Its latest finish time and earliest start time for its successor activity
  • (D) Its earliest finish time and latest start time for its successoractivity

A

Admin • 802.91K Points
Coach

Q. In CPM analysis,

  • (A) Emphasis is given to activities
  • (B) Uncertainties are not allowed
  • (C) Activities are represented by arrows
  • (D) All the above

A

Admin • 802.91K Points
Coach

Q. The estimated time required to perform an activity, is known as

  • (A) Event
  • (B) Dummy
  • (C) Duration
  • (D) Float

A

Admin • 802.91K Points
Coach

Q. Critical Path Net Work helps an engineer

  • (A) To concentrate his attention on critical activities
  • (B) To divert the resources from non-critical advanced activities to critical activities
  • (C) To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
  • (D) All the above