Q. Output of a bulldozeris (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of thetractor Of these statement

  • (A) (i) and (iii) are correct
  • (B) (i) and (iv) are correct
  • (C) (ii) and (iii) are correct
  • (D) (ii) and (iv) are correct

A

Admin • 802.91K Points
Coach

Q. For the execution of a project, a contractor is

  • (A) A person
  • (B) A firm
  • (C) An agency
  • (D) All the above

A

Admin • 802.91K Points
Coach

Q. The constraints in case of resource smoothening operation would be

  • (A) Resources
  • (B) Project duration time
  • (C) Both resources and project duration time
  • (D) None of the above

A

Admin • 802.91K Points
Coach

Q. The time which results in the leasi, possible construction cost of an activity, is known as

  • (A) Normal time
  • (B) Slow time
  • (C) Crash time
  • (D) Standard time

A

Admin • 802.91K Points
Coach

Q. The direct cost of a project with respect to normal time is

  • (A) minimum
  • (B) Maximum
  • (C) Zero
  • (D) Infinite

A

Admin • 802.91K Points
Coach

Q. The object of technical planning, is

  • (A) Preparation of specifications
  • (B) Preparation of estimates
  • (C) Initiating the procurement action of resources
  • (D) All the above

A

Admin • 802.91K Points
Coach

Q. If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

  • (A) 3.5 and 5/6
  • (B) 5 and 25/36
  • (C) 3.5 and 25/36
  • (D) 4 and 5/6

A

Admin • 802.91K Points
Coach

Q. Various activities of a project, are shown on bar charts by

  • (A) Vertical lines
  • (B) Horizontal lines
  • (C) Dots
  • (D) Crosses

A

Admin • 802.91K Points
Coach

Q. Select the correct statement.

  • (A) Activity arrows in a CPM network are drawn to scale
  • (B) The tail of an arrow represents the finish of anactivity
  • (C) Arrow bead represents the start of an activity
  • (D) None of the above

A

Admin • 802.91K Points
Coach

Q. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

  • (A) EF = ES + D
  • (B) LS = LF - D
  • (C) LF = LS + D
  • (D) All the above