Q. Total no of grades for registration of contractor with governments are

  • (A) 3
  • (B) 5
  • (C) 7
  • (D) 4

A

Admin • 802.91K Points
Coach

Q. Contract is terminated in case of

  • (A) Slow progress and time limit exceeds
  • (B) Work is not being executed as per specifications and instruction of EIC
  • (C) Contractor tries to admit sub-contractor
  • (D) All of the above

A

Admin • 802.91K Points
Coach

Q. Mobilization advance

  • (A) Shall be 2 to 5 % of project cost.
  • (B) Shall be 3 to 7 % of project cost.
  • (C) Shall be 10 to 15 % of project cost.
  • (D) Shall be 12 to 18 % of project cost.

A

Admin • 802.91K Points
Coach

Q. Stock account is cleared yearly while tools and plants account is cleared half yearly

  • (A) TRUE
  • (B) FALSE
  • (C) none
  • (D) all

A

Admin • 802.91K Points
Coach

Q. PERT analysis is based upon

  • (A) Optimistic time
  • (B) Pessimistic time
  • (C) Most likely time
  • (D) All of the above

A

Admin • 802.91K Points
Coach

Q. The time activity consumes in most adverse conditions is

  • (A) Optimistic time
  • (B) Pessimistic time
  • (C) Most likely time
  • (D) All of the above

A

Admin • 802.91K Points
Coach

Q. The time activity consumes in normal conditions is

  • (A) Optimistic time
  • (B) Pessimistic time
  • (C) Most likely time
  • (D) All of the above

A

Admin • 802.91K Points
Coach

Q. The difference between the total float and free float is called

  • (A) Duration
  • (B) Interfering float
  • (C) Critical activity
  • (D) None of the above

A

Admin • 802.91K Points
Coach

Q. The critical path is

  • (A) The longest path of the network
  • (B) The shortest path of the network
  • (C) The average duration path of the network
  • (D) None of the above