Q. Updating may result in

  • (A) Change of critical path
  • (B) Decrease of project completion time
  • (C) Increase of project completion time
  • (D) All of the above

A

Admin • 802.91K Points
Coach

Q. The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as

  • (A) Total float
  • (B) Free float
  • (C) Interfering float
  • (D) Independent float

A

Admin • 802.91K Points
Coach

Q. During the construction period, price variation clause in contracts caters to

  • (A) Increase in rates of only importantmaterials
  • (B) Variation in cost in materials element, labour element and petrol-oil-lubricantelement
  • (C) Variation in total cost of the project on an ad hocbasis
  • (D) Rate of inflation

A

Admin • 802.91K Points
Coach

Q. Critical path method

  • (A) Is an improvement upon bar chart method
  • (B) Provides a realistic approach to daily problems
  • (C) Avoids delays which are very common in bar charts
  • (D) All the above

A

Admin • 802.91K Points
Coach

Q. For the network shown in the given figure, the expected time for the activity

  • (A) 1-2 is 4
  • (B) 2-3 is 7
  • (C) 3-4 is 8
  • (D) All the above

A

Admin • 802.91K Points
Coach

Q. A critical ratio scheduling

  • (A) Determines the status of each activity
  • (B) Adjusts automatically changes in activity progress
  • (C) Is a dynamic system
  • (D) None of these

A

Admin • 802.91K Points
Coach

Q. For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is

  • (A) 8 days
  • (B) 9 days
  • (C) 10 days
  • (D) 15 days

A

Admin • 802.91K Points
Coach

Q. In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having

  • (A) Longest duration
  • (B) Highest cost slope
  • (C) Least cost slope
  • (D) Shortest duration

A

Admin • 802.91K Points
Coach

Q. A golden rule for the procurement of construction stones, suggests

  • (A) 100% at the site
  • (B) 67% at the site and 33% under procurement
  • (C) 50% at the site and 50% under procurement
  • (D) 33% at the site and 67% under procurement

A

Admin • 802.91K Points
Coach

Q. The time with which direct cost does not reduce with the increase in time is known as

  • (A) Crash time
  • (B) Normal time
  • (C) Optimistic time
  • (D) Standard time