Q. Which of the following is a parallel activity?

  • (A) Wall construction and carpentary work of doors
  • (B) digging of foundation and construction of a well
  • (C) completion of flooring and plastering of walls
  • (D) completing first floor and starting second floor construction

No solution found for this question.