Q. Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

  • (A) 20
  • (B) 25
  • (C) 35
  • (D) 15