A

Admin • 802.91K Points
Coach

Q. In time-cost optimization of a project, crashing is done.

  • (A) On all the activities
  • (B) On all the activities lying on the critical path
  • (C) Only on activities lying on the original critical path and having flatter costslopes
  • (D) On original critical activities and those that become critical at any stage of crashing inthe order of ascending cost slope

No solution found for this question.
Add Solution and get +2 points.

You must be Logged in to update hint/solution

Discusssion

Login to discuss.

Be the first to start discuss.