Q. In time-cost optimization of a project, crashing is done.
  • A. On all the activities
  • B. On all the activities lying on the critical path
  • C. Only on activities lying on the original critical path and having flatter costslopes
  • D. On original critical activities and those that become critical at any stage of crashing inthe order of ascending cost slope