Q. When float or slack of an activity is positive ?
  • A. it represents a situation where extra resources are available and the completion of project is not delayed
  • B. it represents that a programme falls behind schedule and additional resources are required to complete the project in time
  • C. the activity is critical and any delay in its performance will delay the completion of whole project
  • D. any one of the above