Q. Which of the following statement is correct ?
  • A. When float of an activity is zero, it falls only on critical path
  • B. CPM technique is useful to minimise the direct and indirect expenses
  • C. Critical path of a net work represents the minimum time required for completion of project
  • D. all of the above