Q. The reduction in project time normally results in
  • A. Decreasing the direct cost and increasing indirect cost
  • B. Increasing the direct cost and decreasing the indirect cost
  • C. Increasing the direct cost and indirect cost both
  • D. Decreasing the direct cost and indirect cost both