Home / Report Question

Q. Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.
  • A. A is correct but R is not correct
  • B. R is correct but A is not correct
  • C. Both A and R is correct
  • D. Both A and R is incorrect