Q. A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now so that the work may finish in time ?

  • (A) 48
  • (B) 56
  • (C) 40
  • (D) 50
  • Correct Answer - Option(B)