Q. A and B can do a piece of work in 6 days and A alone can do it in 9 days. The time taken by B alone to do the same work is ?

  • (A) 18 days
  • (B) 15 days
  • (C) 12 days
  • (D) 7.5 days
  • Correct Answer - Option(A)
  • Views: 12
  • Filed under category Math