Q. x does 1/4 of a job in 6 days. y completes rest of the job in 12 days. Then x and y could complete the job together in = ?

  • (A) 9 days
  • (B) 8 1/8 days
  • (C) 9 3/5 days
  • (D) 7 1/3 days
  • Correct Answer - Option(C)
  • Views: 5