Q. P can complete 1/4 of a work in 10 days, Q can complete 40% of the same work in 145 days. R, complete 1/3 of the work in 13 days and S, 1/6 of the work in 7 days. Who will be able complete the work first ?
- Correct Answer - Option(C)