Q. A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?

  • (A) 11:30 A.M.
  • (B) 12 Noon
  • (C) 12:30 P.M.
  • (D) 1:00 P.M.
  • Correct Answer - Option(D)