Q. A and B alone can complete work in 9 days and18 days respectively. They worked together; however 3 days before the completion of the work A left. In how many days was the work completed ?

  • (A) 8 days
  • (B) 6 days
  • (C) 5 days
  • (D) 13 days
  • Correct Answer - Option(A)