Q. To complete a piece of work A and B take 8 days, B and C 12 days. A, B and C take 6 days. A and C will take :

  • (A) 7 Days
  • (B) 7.5 Days
  • (C) 8 Days
  • (D) 8.5 Days
  • Correct Answer - Option(C)